Florida Notice to Owner and Lien
Timeline Calculators |
| |
|
Need more information about Florida
Construction Lien Law?
Refer
to Florida Statute § 713  |
| |
|
The Florida Notice to Owner must be
filed within 45 days of first providing labor, services or materials
on the
project to preserve your lien rights. |
| |
|
The Florida Claim of Lien may be recorded at any
time during the progress of the work or not later than 90 days
after
the final
furnishing of the labor, services for materials. |
| |
|
Last Day on the Job: |
|